Contractors recently completed a foundation pour for the 70-story Okan Tower, which is set to reach a height of 902 feet in the air.
It will be one of Miami’s tallest towers when it reaches completion, which is now planned for 2027, the developer said in a statement yesterday.
Okan Tower is planned to include 163 residential units, 236 short-term rental residences managed by Hilton, and a 316-key Hilton Miami Bayfront Hotel along with 64,000 square feet of Class A office space.
For the foundation pour, 12,000 cubic yards of concrete was poured, with 2,300 tons of high strength reinforcing steel placed.
The 36-hour continuous pour began on Friday, March 29. A crew of 300 workers across three shifts completed the job with the help of 1,200 concrete trucks.
General contractor Jacob Companies joint ventured with Okan Construction oversaw the pour.
Okan Group is the developer.